The risk register is the proactive heart of the SMS: a hazard log where every identified hazard carries a risk assessment, mitigation and a review rhythm. The page has two tabs: the Hazard log itself, and Assessed occurrences — occurrences from the register that carry a risk assessment, sorted by residual risk, so the reactive picture is always visible next to the proactive one.
The log shows per hazard its reference (H-2026-0001 style), the initial and residual risk badge, the next review date and the status. Counting tiles on top break the register down per matrix colour and flag hazards due for review.
Recording a hazard
Add hazard asks for more than a title, because a well-described hazard is half the assessment:
- Hazard title and description — what can go wrong.
- Worst credible outcome — the realistic worst case, which anchors the severity score.
- Existing barriers — what already stands between the hazard and that outcome.
- Area (operation) — where it plays (runway operations, maintenance, training, …).
- Source — how it was identified: proactively, from an occurrence, from an audit, or from a change. Hazards created from an occurrence or change keep that link automatically.
- Owner and review interval — who watches it, and how often it is re-examined.
Risk assessment
Assessment follows the ICAO 5×5 matrix: a severity from A (Catastrophic) to E (Negligible) and a likelihood from 1 to 5 combine into a badge such as 3C, coloured by matrix region (red = intolerable, amber = tolerable with mitigation, green = acceptable). The severity scale carries concrete anchors — injuries, environmental impact, financial damage bands — so different assessors classify consistently.
Each hazard is scored twice: the initial risk (before mitigation) and the residual risk (after). The register shows both badges side by side, which makes it immediately visible what your mitigations actually achieve — and which hazards only look handled.
The hazard detail
A hazard opens in a split view with tabs:
- Hazard — the descriptive fields, owner, status and review date.
- Risk assessment — the matrix, with a toggle between the initial and residual score.
- Mitigation — the actions that reduce the risk, each with an owner, due date and open/closed status; overdue actions are flagged. Closing an action requires a closing note — what was actually done is the evidence — and the safety manager can schedule an effectiveness check a few months out: a formal effective / not effective verdict, where "not effective" reopens the action.
- Occurrences — linked occurrences; the link can be made from either side, so a new report lands directly under the hazard it confirms.
- Evidence — supporting documents uploaded directly on the hazard: risk studies, photos, procedures.
Statuses, acceptance and review
A hazard is Open, Monitoring, Accepted or Archived.
Accept residual risk is the formal step, reserved for the safety manager: it requires a scored residual risk and a written acceptance note, records who accepted what and when, and schedules the next review one interval ahead. Re-scoring the risk after acceptance deliberately undoes the acceptance — the hazard drops back to Monitoring, because an acceptance of a different number is not an acceptance of this one.
Every hazard carries a review date. The Hazards due review tile — in the register and on the dashboard — turns red when reviews are overdue, and the weekly digest e-mail lists them, so the register never silently goes stale. Archived hazards leave the working set but keep their full history.