Management of change (MoC) is the SMS answer to "we are about to change something": a new fuel installation, a changed runway procedure, a new aircraft type, a reorganisation. Each change is assessed for the hazards it introduces before it goes ahead, the go/no-go is a recorded decision, and every implemented change is reviewed afterwards. Changes get a reference (CH-2026-0001 style); counting tiles on the list page show how many sit in each stage.
Describing a change
A change records its title, description and reason, the affected areas, a change type (organisational, operational, technical or infrastructure), the planned date and an owner. If the authority is involved, that is part of the record too: no involvement, notification, or prior approval, with the authority's reference and date — so the dossier shows at a glance whether the regulatory side is covered.
The workflow
| Status | What happens |
|---|---|
| In assessment | The change is described and its safety assessment is built |
| Awaiting decision | Formally submitted; the safety manager decides to proceed or not |
| Implementation | Approved and being carried out; actions track the work |
| Post-review | Implemented — awaiting the post-implementation review on its planned date |
| Closed / Rejected / Cancelled | Final states; the dossier stays readable |
A workflow banner on the detail page always names the current stage and offers the next step. The guards are deliberate:
- Submitting for decision is blocked until every linked hazard has a residual assessment — the safety assessment is not optional paperwork. A submitted change can be withdrawn back to assessment.
- The decision requires the safety settings permission plus a written verdict and note — who decided, what, and why, is permanent record.
- Mark implemented records the implementation date and automatically schedules the post-implementation review (default six months later; the interval is configurable per change).
- The post-review requires a written note and ends in one of two outcomes: close the change, or reassess — which sends it back to assessment because reality did not match the plan. Overdue post-reviews are flagged on the list, the dashboard (Changes needing attention: awaiting decision + overdue post-reviews) and the weekly digest.
The safety assessment
The Safety assessment tab reuses the risk register rather than inventing a parallel one: New hazard from this change creates a hazard with source change and the link in place; Link existing hazard attaches one already in the register. Each hazard is assessed there — initial and residual — and keeps living in the register after the change closes, which is exactly what you want: the change ends, the hazard remains managed.
Actions, documents and the dossier
- Actions — implementation and mitigation actions with owners and due dates, closed with a closing note like everywhere else in the module.
- Documents — supporting material uploaded directly on the change: procedures, drawings, and the correspondence with the authority.
- Dossier PDF — one click generates the complete change dossier: the change and its authority trail, every hazard with its assessments, mitigations and acceptances, the decision, implementation and post-review, and the document list. That is the file you hand the auditor.